Capital construction case · 2026

Kyiv School No. 24: UAH 195 million expected value for a dual-purpose structure with PRU protective properties

This is a useful example of a large capital project where the procurement is not a ready-made module supply. The subject is construction of a dual-purpose structure with anti-radiation shelter (PRU) protective properties for a school.

What the public procurement justification states

  • contracting authority: Education Department of the Shevchenkivskyi District State Administration in Kyiv;
  • procurement identifier: UA-2026-05-18-010692-a;
  • subject: construction of a dual-purpose structure with PRU protective properties for Specialized School No. 24 named after O. Bilash;
  • CPV category: engineering and construction works;
  • expected value: UAH 195,000,000 including VAT;
  • the expected value was based on project documentation and a positive expert report;
  • the procurement documentation states a works period extending to 21 December 2027.

Why UAH 195 million is not a universal 'shelter price'

This procurement covers a capital engineering and construction project. Such a budget can include earthworks, structural works, engineering systems, finishes, commissioning and other scope defined by the project and estimate documentation.

Comparing this amount directly with the price of one or more factory modules would mix different procurement categories and different end results.

Why ShelterMetric does not calculate a cost per place here

The public justification used as the primary source does not present capacity as a sufficiently clear standalone figure for a responsible unit-cost calculation. ShelterMetric does not invent a number of occupants simply to produce an attractive UAH-per-place metric.

What this case teaches a buyer

  • capital construction should be compared with other capital construction of a similar scope;
  • a project estimate and expert review can be part of how the expected procurement value is established;
  • the generic word shelter is not enough to make two procurements comparable;
  • before comparing price, identify whether the procurement is goods supply, supply plus installation, reconstruction or full construction.